Situation | Practical consequence |
SME under the EU definition | No EDL-G audit obligation solely by virtue of SME status; check other applicable energy rules. |
Non-SME with annual total energy consumption up to 500,000 kWh | The simplified online declaration can satisfy the EDL-G audit obligation; this is not a full audit. |
Non-SME above 500,000 kWh, without a qualifying management system | Commission a DIN EN 16247-1 audit and repeat it at least every four years. |
Company averaging more than 7.5 GWh per year over three completed calendar years | The EnEfG requires an energy or environmental management system; its rules interact with the EDL-G audit obligation. |
Cost driver | Why it changes the quote |
Sites and their similarity | Repeated store formats may allow sampling; diverse factories or buildings need separate analysis. |
Energy data quality | Missing bills, submetering or load data increases collection and reconstruction work. |
Technical complexity | Process heat, refrigeration, HVAC, production and transport need different expertise. |
Visits and deliverables | Travel, measurements, site access, reporting and a presentation affect the scope. |