Field | What to record |
Contract and inspection | Project, trade or defined section, parties, date, attendees and inspected scope. |
Decision | Accepted, refused with identified significant defects, or a specifically agreed follow-up procedure. |
Defects and reservations | Precise location and description, photographs, contractor, cure date and reservation of rights for known defects. |
Tests and documents | Functional tests, commissioning results, missing records, keys and asset data. |
Close-out | Who checks the remedy, how completion is recorded and which items pass to building operations. |
Issue | BGB building contract | Effective VOB/B |
Typical limitation for building defects | Generally five years from acceptance under § 634a BGB. | Generally four years from acceptance if the contract sets no different period under § 13(4) VOB/B. |
Acceptance procedure | § 640 BGB; refusal requires at least one named defect for the deemed-acceptance mechanism. | § 12 VOB/B provides formal and deemed-acceptance routes with specific conditions and periods. |
Defect demand | Seek subsequent performance and normally set a reasonable cure deadline before self-remedy. | Written demand before expiry under § 13(5) VOB/B; then set a reasonable cure deadline for the next step. |